1 General Provisions
2 Basic Requirements
3 Equipment Foundation,Anchor Bolt and Base Plate
3.1 Equipment Foundation Construction
3.2 Inspection and Acceptance of Equipment Foundation
3.3 Erection of Anchor Bolts
3.4 Inspection and Acceptance of Anchor Bolts
3.5 Erection of Base Plates
3.6 Inspection and Acceptance of Base Plates
4 Equipment and Materials Mobilization
4.1 General Requirements
4.2 Inspection and Acceptance of Equipment and Materials
5 Equipment of Pipe Billet Preparation Section
5.1 Installation of Short/Long Band Sawing Machine
5.2 Inspection and Acceptance of Short/Long Band Sawing Machine
5.3 Installation of Peeler
5.4 Inspection and Acceptance of Peeler
5.5 Installation of Facing Machine
5.6 Inspection and Acceptance of Facing Machine
5.7 Installation of Center Hole Drilling Machine
5.8 Inspection and Acceptance of Center Hole Drilling Machine
5.9 Installation of Deep Hole Drilling Machine
5.10 Inspection and Acceptance of Deep Hole Drilling Machine
5.11 Test-run of Equipment of Pipe Billet Preparation Section
6 Punching and Expanding Press
6.1 Installation of Base
6.2 Inspection and Acceptance of Base
6.3 Installation of Machine Frame
6.4 Inspection and Acceptance of Machine Frame
6.5 Installation of Upsetting Beam/Piercing Beam
6.6 Inspection and Acceptance of Upsetting Beam/Piercing Beam
6.7 Installation of Container
6.8 Inspection and Acceptance of Expanding Container
6.9 Installation of Manipulator
6.10 Inspection and Acceptance of Manipulator
6.11 Installation of Glass Powder Lubrication Table
6.12 Inspection and Acceptance of Glass Powder Lubrication Table
6.13 Test-run of Punching and Expanding Press
7 Extrusion Press
7.1 Installation of Base Board
7.2 Inspection and Acceptance of Base Board
7.3 Installation of Front and Back Beams
7.4 Inspection and Acceptance of Front and Back Beams
7.5 Installation of Pre-tensioned Column
7.6 Inspection and Acceptance of Pre-tensioned Column
7.7 Installation of Extrusion Beam
7.8 Inspection and Acceptance of Extrusion Beam
7.9 Installation of Piercing Beam
7.10 Inspection and Acceptance of Piercing Beam
7.11 Installation of Container
7.12 Inspection and Acceptance of Extrusion Container
7.13 Installation of Manipulator
7.14 Inspection and Acceptance of Manipulator
7.15 Installation of Main Hydraulic Cylinder
7.16 Inspection and Acceptance of Main Hydraulic Cylinder
7.17 Installation of Glass Powder Lubrication Table
7.18 Inspection and Acceptance of Glass Powder Lubrication Table
7.19 Test-run of Extrusion Press
8 Auxiliary Equipment of Extrusion Line
8.1 Installation of Charging Unit and Pipe Billet Cleaning Unit
8.2 Inspection and Acceptance of Charging Unit and Pipe Billet Cleaning Unit
8.3 Installation of Conveying Roller Table
8.4 Inspection and Acceptance of Conveying Roller Table
8.5 Inspection of Induction Heating Furnace
8.6 Inspection and Acceptance of Induction Heating Furnace
8.7 Installation of High-pressure Descaling Unit
8.8 Inspection and Acceptance of High-pressure Descaling Unit
8.9 Installation of Quenching Tank
8.10 Inspection and Acceptance of Quenching Tank
8.11 Installation of Chain Type Cooling Bed
8.12 Inspection and Acceptance of Chain Type Cooling Bed
8.13 Test-run of Auxiliary Equipment of Extrusion Line
9 Rotary Heating Furnace
9.1 Installation of Furnace Steel Structure
9.2 Inspection and Acceptance of Furnace Steel Structure
9.3 Installation of Feeding and Tapping Roller Table
9.4 Inspection and Acceptance of Feeding and Tapping Roller Table
9.5 Installation of Backup Rollers and Guide Rollers
9.6 Inspection and Acceptance of Backup Rollers and Guide Rollers
9.7 Erection of Rotating Steel Platform
9.8 Inspection and Acceptance of Rotating Steel Platform
9.9 Installation of Trolley
9.10 Inspection and Acceptance of Trolley
9.11 Erection of Furnace Shell
9.12 Inspection and Acceptance of Furnace Shell
9.13 Installation of Furnace Door and Lifting Units
9.14 Inspection and Acceptance of Furnace Door and Lifting Units
9.15 Test-run of Rotary Heating Furnace
10 Finishing Line Equipment
10.1 Installation of Pressure Straightener
10.2 Inspection and Acceptance of Pressure Straightener
10.3 Installation of Inclined Roller Straightener
10.4 Inspection and Acceptance of Inclined Roller Straightener
10.5 Installation of Pipe Cutting Band Sawing Machine
10.6 Inspection and Acceptance of Pipe Cutting Band Sawing Machine
10.7 Installation of Shot Blasting Machine