6.7 Installation of Container

6.7.1 The container shall be installed after the installation of upsetting beam/piercing beam is completed.

6.7.2 When adjusting the levelness of container,the upper machined surface of equipment shall be taken as the datum point.

6.7.3 It is necessary to use the inside micrometer to examine the axiality between the container and the upsetting pole.