10.4 Furnace Cover and Furnace Cover Lifting Mechanism
Ⅰ Dominant Items
10.4.1 The hydrostatic test and flushing test of water-cooled parts of furnace cover shall meet the requirement of Article 9.6.5 of the Code.
Ⅱ General Items
10.4.2 The allowable deviation for installation of furnace cover and furnace cover lifting mechanism shall comply with the requirements in Table 10.4.2.
Quantity to be checked:100%.
Inspection method:see Table 10.4.2.
Table 10.4.2 Allowable deviation for installation of furnace cover and furnace cover lifting mechanism