GB50551-2010球团机械设备安装工程质量验收规范(英文版)
上QQ阅读APP看本书,新人免费读10天
设备和账号都新为新人

4.2 Equipment Foundation

Ⅰ Major Items

4.2.1 Strength of equipment foundation shall meet the requirements of design technical documents.

Quantity checked:All.

Checking method:Check handover foundation documents.

4.2.2 Layout of central scale plate and elevation datum points shall be drawn according to construction drawings and surveying control network before equipment placement.Central scale plate and elevation datum points shall be set according to the layout with measurement and placement.Major equipments and consecutive production lines shall embed permanent central scale plates and elevation datum points.

Quantity checked:All.

Checking method:Check measurement records and by observation.

Ⅱ General Items

4.2.3 The locations of foundation axis,elevation,size and locations of anchor bolts of equipment foundations shall meet the requirements of design technical documents and current national standard GB 50231 General Code for Construction and Acceptance of Mechanical Equipment Installation Engineering.

Quantity checked:All.

Checking method:Check reexamination records.

4.2.4 Greasy dirt,crushed stones,soil,water,etc.on the surface of equipment foundations and in preformed holes of anchor bolts shall all be cleaned.Pre-buried anchor bolts and nuts shall be in complete protection.

Quantity checked:All.

Checking method:Check by observation.