6.5 Nitrogen Sealing Device

Ⅰ Dominant Items

6.5.1 The orifice of nitrogen sealing ring shall be unobstructed

Quantity to be checked:100%.

Inspection method:Observe.

Ⅱ General Items

6.5.2 The allowable deviation for installation of nitrogen sealing ring shall comply with the requirement in Table 6.5.2.

Quantity to be checked:100%.

Inspection method:See Table 6.5.2.

Table 6.5.2 Allowable deviation for installation of nitrogen sealing ring